Starting November 2025, the Salina Public Library will begin Re-Imagining our Youth Services space. Follow along here for the latest remodel updates and what to expect!
Youth Services Remodel Updates
What to Expect
- Some programs are temporarily relocating.
Check the online calendar to see up-to-date information on where programs are being held. - Some rooms are temporarily unavailable for reservation.
The Prescott Room and Technology Conference Room are not reservable at this time. - Youth and Teen materials are relocated to the main floor.
Youth and Teen materials can be found on the east side of the main floor, where adult media was previously located. Library staff are happy to assist you in finding materials, or let us do the searching for you by placing a hold. - Adult Media is located near adult fiction and nonfiction.
Library staff are happy to assist you in finding materials, or let us do the searching for you by placing a hold.
Learn how to Manage your Holds here.
- Construction Noise
There may be an increase in noise during hours of operation. - Reduced Seating
There may be fewer available seating options as all collections will be temporarily relocated to the main floor.
Thank you for your patience and flexibility throughout this exciting transition!
Updates
- May 29, 2026: Lighting and HVAC grilles have continued to be added, while carpet and LVT flooring is being laid throughout the stacks area. The last of the aluminum storefront was installed, and the main desk and cabinets were all set. Final painting of walls and soffits has started, as well as cabinet and trim painting within the Prescott Room.
- May 15, 2026: Received delivery of millwork items and started setting cabinets in preparation for next week’s countertop templating. The last of the floor prep and leveling is taking place ahead of LVT/carpet flooring.
- May 8, 2026: All remaining can-light rough-in boxes have been installed. Floor preparation has begun. Aluminum storefront framing has started at the meeting, programming, and teen room openings, and door installation continued with new hardware being fitted.
- April 24, 2026: All tiling is complete, and painting has begun. Fixtures and ceiling grid installation have started.
- March 13, 2026: Plumbing and electrical in-wall rough-ins were completed and inspected.
- Feb. 20, 2026: Stud framing complete
- Feb. 2, 2026: Demolition complete
- Jan. 5, 2026: Construction on the Youth Services space has begun. The lower level will be inaccessible until construction is complete.
- Nov.17, 2025: Library Closed to allow for material transition on the main level.
- Aug. 1, 2025: All book donations paused to help free up storage space.
Remodel Images
We’re almost there! Help us raise the final funds needed to bring this new space to life! Join the mission and make dreams come true for kids and teens by giving today.